Updates to the New Wing Luke Design

The New Wing Luke Design Begins to Take Shape
Posted on 03/09/2017
The new Wing Luke design in progress

Opened in 1971, the current Wing Luke faces several systems and structural challenges. The building will be removed in late 2018 and a new elementary school is scheduled to open in its place in time for the 2020 school year.

Follow the latest news on the Wing Luke Building Excellence home page.

Budget

$43.2 million

Project

Replace the deteriorating buildings of Wing Luke with a new school that supports best learning practices for elementary schools. The new building capacity will be 500-600 students, providing additional permanent capacity to support projected enrollment growth in southeast Seattle.

After abating and demolishing the existing structures, core facilities and teaching areas will be built and site work completed.

Schedule Overview

Estimated design work start: September 2015

Estimated construction start: November 2018

Estimated school opening: Fall 2020