    Wing Luke Construction Project Update
    Posted on 04/24/2020
    Wing Luke Building Rendering

    BEX IV Capital Levy Wing Luke Elementary School Replacement Projectpdf icon

    Site – Completed courtyard retaining wall

    Envelope – Continuing roofing on A + B; started roofing on C; started brick veneer, metal cladding, and windows on A + B; completed exterior framing, sheathing, and started Water Resistive Barrier/Air Barrier (WRB/AB) on C

    Building A – Installed stair 1; continuing Mechanical, Electrical, Plumbing, and Fire Suppression (MEPF) rough ins and conducting verification tests; completed electrical boxing; started wall assembly insulation and Gypsum Wallboard (GWB)

    Building B – Installed stair 2; completed interior framing; continuing MEPF rough ins

    Building C – Placed concrete for stage steps; installed stair 3; completed interior framing; started MEP rough ins; completed fire suppression rough in